I have attached the most up to date floor plans for levels 2 and 3 for you all to have a look at. Also the first carpet tiles were glued down on level 4 today and some shelving is up. I thought you all might like to have a look at it.
As the loft is no longer on level 5 levels 2 and 3 have an increased number of computers. There will eventually be at least 160 computers. The area where QH-R are currently shelved may not be clear by the time we open on 21 February. The budget for the purchase of some new furniture drawn on these plans has not yet been allocated. The copy centre is moving back into the library the week beginning 14 February.
The colours for the artwork on the glass entrance and high demand area are in the level 5 staffroom if you want to take a look.
Joan
Nice carpet! Alas the documents you’ve linked to are in your P:drive so we have no access…
Deborah
Thanks Deborah. I have fixed this now.