PJH Level 2 development update #2

W3lc0m3 to update #2.  There has been steady progress made and work will ramp up as we move closer to Christmas.  FM will begin installing plastic sheeting this week, and will be on site next week to progress the remodelling of Te Rua.  Please continue to be aware of work underway on level.  New status updates are in bold below.

Te Rua Makerspace

  1. Clearing out the Den and surrounding area. Completed
  2. Removal of art works from the Den walls. To be completed today
  3. Removal of ‘The Den’ from the library room bookings. Completed.
  4. Notification to Academic skills of construction and possible noise over summer. Completed.
  5. Notification to Space Manager and Timetabling of changes to the Den and the new Te Rua. Completed.
  6. Notices drafted for Library users that the area is under construction. Completed.

Furniture reshuffle

  1. Moving tables and chairs, and casual seating to keep a clear space for construction. In progress
  2. Blue couches and chairs get a makeover.  In progress
  3. Cleaning of tables, and walls as needed.  In progress

Decanting Self Loan/High Demand

  1. Beims to move Self Loan machines.
  2. ITS will move MFD.
  3. Move items on rear shelves to the front shelves.
  4. Dismantle rear shelves.
  5. Move VHS and CD Collections. In progress