We are now up to the Learning Spaces part of phase one of this 5 year project. This week new furniture pods are being installed on Level 10 of PJH. It is very exciting to see this progress. See photos below of pods. The move and shuffle of materials on levels 9 to 11 is now complete. There are still some boxes to unpack in Henry Field Store.
For those of you interested in statistics, this is what the project has achieved so far in the last year:
- Withdrawn 82,000 items (from Store H and PJH)
- Relegated and moved 27,000 items from PJH to Store H
- Shuffled and moved 155,000 items on Levels 9 to 11
- Packed items into and out of 1700 boxes, and constructed & dismantled the boxes again.
- Dismantled and removed 98 bays of shelving from L10
- Employed 2800 hours of casual staff plus many hours of permanent staff time.