PJH Level 2 update #4

W3lc0m3 to update #4. Room 224 (old high demand) is now a 52 seater room with tables, 214 has 8x student bookable study rooms, 2x Ātea ako Subject Librarian consultation rooms, and 2x IT Help consultation rooms. New status updates are in bold below.

Te Rua Makerspace
1. Construction of Te Rua Makerspace. Plastering and painting in progress. Glazing, flooring and ceiling rigging to be progressed. Slippage in time due to other UC priorities. Expected completion is after 17 February but before March.

Furniture reshuffle
1. Blue couches and chairs re-upholstery – picked up in December 2019 with ETA of January/February. These will be used for the 214 waiting area and other casual seating on level 2 and 3 when they return. Delayed delivery.

Decanting Self Loan/High Demand
1. Beims to move Self Loan machines. Completed
2. ITS will move MFD. Completed
3. Move items on rear shelves to the front shelves. Completed
4. Dismantle rear shelves. Completed
5. Move VHS and CD Collections. Completed – DVD collection moved to level 7, VHS moved to Store, Music collection moved to reading space level 2
6. Mobile shelving delivery is expected in the week beginning 13 January. These will house high demand and holds and be located behind the info desk. A space has been cleared for this shelving. Completed
7. AV and blu-ray machine location.

W3lc0m3 to update #4.  Room 224 (old high demand) is now a 52 seater room with tables, 214 has 8x student bookable study rooms, 2x Ātea ako Subject Librarian consultation rooms, and 2x IT Help consultation rooms.  New status updates are in bold below.

Te Rua Makerspace

  1. Construction of Te Rua Makerspace. Plastering and painting in progress.  Glazing, flooring and ceiling rigging to be progressed. Slippage in time due to other UC priorities.  Expected completion is after 17 February but before March.

Furniture reshuffle

  1. Blue couches and chairs re-upholstery – picked up in December 2019 with ETA of January/February. These will be used for the 214 waiting area and other casual seating on level 2 and 3 when they return.  Delayed delivery.

Decanting Self Loan/High Demand

  1. Beims to move Self Loan machines. Completed
  2. ITS will move MFD. Completed
  3. Move items on rear shelves to the front shelves. Completed
  4. Dismantle rear shelves. Completed
  5. Move VHS and CD Collections. Completed – DVD collection moved to level 7, VHS moved to Store, Music collection moved to reading space level 2
  6. Mobile shelving delivery is expected in the week beginning 13 January. These will house high demand and holds and be located behind the info desk.  A space has been cleared for this shelving. Completed
  7. AV and blu-ray machine location. In progress

Rooms 214 (Temporary Makespace area)

  1. 214 A-H will be 8 student bookable study rooms with an occupancy of 4 people each. These will be added to the library bookings for start of semester 1. Completed
  2. 214 I & J use changed and these are now designated for IT Help consultations. Completed – IT to install furniture for start of Semester 1. IT will move from the info desk after the first two weeks and be based in the 214 rooms.  They will also have 2x self-service kiosks in the 214 waiting area.
  3. 214 K & L will be used for Ako Ātea – 2x consultation rooms for subject librarians to use. Completed – these are now operational.
  4. The main doors to 214 will be removed to open up the space and increase visibility. Completed – in addition, the main doors to 212 discussion rooms have also been removed. In progress

 

PJH Level 2 update #3

W3lc0m3 to update #3. FM has the plastic sheeting up, and the old den has been removed. Construction on Te Rua Makerspace is in full swing. It is anticipated this work will continue through to February. New status updates are in bold below.

Te Rua Makerspace
1.  Clearing out the Den and surrounding area. Completed
2.  Removal of art works from the Den walls. Completed
3.  Removal of ‘The Den’ from the library room bookings. Completed.
4.  Notification to Academic skills of construction and possible noise over summer. Completed.
5.  Notification to Space Manager and Timetabling of changes to the Den and the new Te Rua. Completed.
6.  Notices drafted for Library users that the area is under construction. Completed.
7.  Construction of Te Rua Makerspace. In progress – expected to continue through to February.

Furniture reshuffle
1.  Moving tables and chairs, and casual seating to keep a clear space for construction. Completed
2.  Blue couches and chairs get a makeover. Removed and being reupholstered.
3.  Cleaning of tables, and walls as needed. Completed
4.  The newspapers, jigsaw, chess etc have now moved to their new home on level 2. It is now in the reading space by the portrait of James Hight. Please direct people to this space so they can catch up on news or relax and read. This will also be the space where we will display any new physical materials for the library. Completed
5.  Curious cabinet will move around the corner from its current location freeing up the wall for a painted interactive mural that Gavin, Rā and team are working on. In progress
6.  Level 3 old brown single tables have been removed and replaced with kite tables or better tables. Light green ottomans have also been removed from level 3. Completed
7.  Level 2 layout reconfigured to create a reading space, space for mobile shelving, returned today mobile shelving Completed
8.  The newspapers, jigsaw, chess etc have now moved to their new home on level 2. It is now in the reading space by the portrait of James Hight. Completed

Decanting Self Loan/High Demand
1.  Beims to move Self Loan machines. In progress
2.  ITS will move MFD. In progress
3.  Move items on rear shelves to the front shelves. Completed
4.  Dismantle rear shelves. Completed
5.  Move VHS and CD Collections. In progress
6.  Mobile shelving delivery is expected in the week beginning 13 January. These will house high demand and holds and be located behind the info desk. A space has been cleared for this shelving.
7.  AV and blu-ray machine location.

Rooms 214 (Temporary Makespace area)
1.  214 A-H will be 8 student bookable study rooms with an occupancy of 4 people each. These will be added to the library bookings for start of semester 1. In progress
2.  214 I & J is used for customer services store for engagement resources, signage, wellbeing resources, disaster tarp etc, PJH copy paper and toner. Completed
3.  214 K & L will be used for Ako Ātea – 2x consultation rooms for subject librarians to use. It is anticipated that Academic Skills will use one of these rooms for consultations when they resume their extended hours service that they trialled in 2018. In progress
4.  The main doors to 214 will be removed to open up the space and increase visibility. Flagged for February

MakerSpace Facilitator

Gavin has tendered his resignation and this has been accepted. He has received an opportunity to good not to accept, which enables him to work closer to home and family. Gavin has been fantastic in the role and we wish him every success with his new role.

Gavin’s last working day will be 17 January 2020.  A morning tea will be arranged in due course and all are welcome.

The MakerSpace Facilitator role is expected to be advertised soon and we hope to make an appointment in January.

Makerspace Facilitator appointment

We are delighted to share that Gavin Hewitt has been appointed in the continuing full time position of Makerspace Facilitator, with a start date of Thursday 5 December 2019. We look forward to building on the progress made with the pilot makerspace project as we transition into a larger fit for purpose space for creative interdisciplinary learning.

PJH Level 2 development update #2

W3lc0m3 to update #2.  There has been steady progress made and work will ramp up as we move closer to Christmas.  FM will begin installing plastic sheeting this week, and will be on site next week to progress the remodelling of Te Rua.  Please continue to be aware of work underway on level.  New status updates are in bold below.

Te Rua Makerspace

  1. Clearing out the Den and surrounding area. Completed
  2. Removal of art works from the Den walls. To be completed today
  3. Removal of ‘The Den’ from the library room bookings. Completed.
  4. Notification to Academic skills of construction and possible noise over summer. Completed.
  5. Notification to Space Manager and Timetabling of changes to the Den and the new Te Rua. Completed.
  6. Notices drafted for Library users that the area is under construction. Completed.

Furniture reshuffle

  1. Moving tables and chairs, and casual seating to keep a clear space for construction. In progress
  2. Blue couches and chairs get a makeover.  In progress
  3. Cleaning of tables, and walls as needed.  In progress

Decanting Self Loan/High Demand

  1. Beims to move Self Loan machines.
  2. ITS will move MFD.
  3. Move items on rear shelves to the front shelves.
  4. Dismantle rear shelves.
  5. Move VHS and CD Collections. In progress

PJH Level 2 development update

Work to transform Te Rua Makerspace on PJH level 2 is expected to start soon.  This transformation aims to create a larger, fit for purpose makerspace over the summer so this means some reshuffling of equipment and furniture.  We will also start decanting the self-loan/high demand area.

Please be aware of these changes that are going on, and if you have bookings in the Den within the next two weeks, these may be affected.

Regular counterculture posts will be made over the summer to keep you in the loop.

Some of the things that will get underway soon include:

Te Rua Makerspace

  1. Clearing out the Den and surrounding area. ITS will start to move PC’s, MFD’s, and AV soon.  This will prepare the room for the remodelling phase led by FM.  We hope to have this completed by early December 2019.
  2. Removal of art works from the Den walls. In progress.
  3. Removal of ‘The Den’ from the library room bookings. Completed.
  4. Notification to Academic skills of construction and possible noise over summer. Completed.
  5. Notification to Space Manager and Timetabling of changes to the Den and the new Te Rua. Completed.
  6. Notices drafted for Library users that the area is under construction. Completed.

Furniture reshuffle

  1. Moving tables and chairs, and casual seating to keep a clear space for construction.
  2. Blue couches and chairs get a makeover.  Working with Tracy Ford to get these recovered in Jan/Feb.

Decanting Self Loan/High Demand

  1. Beims to move Self Loan machines.
  2. ITS will move MFD.
  3. Move items on rear shelves to the front shelves.
  4. Dismantle rear shelves.
  5. Move VHS and CD Collections.

Makerspace Facilitator – continuing opportunity

We have an exciting opportunity for a full-time continuing Makerspace Facilitator in the customer services team. In this role, you will be responsible for creating and supporting an innovative, creative, collaborative and engaging environment for students and staff to explore ideas, research opportunities, which in turn will enhance student success.  The Makerspace Facilitator will genuinely engage with students’ ideas, their development and applications in a fit for purpose space and utilising blended online learning, and multi-disciplinary learning. 

Further information about this opportunity is available on the UC Job Vacancies website.  Job ID 7807, Makerspace Facilitator