Update: Uni-Cycle work, University Drive one-way extended

Many of you will have seen construction work is progressing on the Uni-Cycle Major Cycleway route along University Drive. The next stage of work is due to start tomorrow (15 December) and will see the current one-way system in place on University Drive extended.

  • When extended the one-way system on University Drive, heading east towards Clyde Road, will be in place between the Health Centre pedestrian bridge (opposite the ICT car park) and Clyde Road. (See image below)
  • A 20km/h speed limit will be in place through the one-way section for the duration of the works.
  • There will continue to be no entry from Clyde Road onto University Drive.
  • Two way traffic will remain on University Drive between Ilam Road and the Health Centre pedestrian bridge/ICT car park.

Car park access

  • Vehicles coming from Clyde Road should continue to access the Clyde Car Park via Arts Road. Vehicles exiting the Clyde Car Park onto University Drive will not be able to turn right (towards Ilam Road) – left  turn only towards Clyde Road.
  • Access to the Law Car Park will be via Ilam Road and the west entrance/exit (near the Music building) only. The east entrance/exit (closest to Clyde Road) will be closed. Vehicles exiting the Law Car Park will not be able to turn right (towards Ilam Road) – left turn only towards Clyde Road.

Pedestrians

  • The footpath on the southern side of University Drive between the Health Centre bridge and Clyde Road will be closed.
  • Please walk through campus via the signed detour route (see image below) or via Kirkwood Ave when heading east or west between Ilam and Clyde roads.
  • Access across all three pedestrian bridges (UCSA, Health Centre and Recreation Centre) will remain open.

Cyclists

  • There is no access to University Drive from Clyde Road. Please use Arts Road or Kirkwood Ave instead, or follow the pedestrian detour.
  • When heading east (towards Clyde Road), cyclists can use the one-way system in place along University Drive.
  • Cyclists travelling between Ilam and Clyde roads (in either direction) can use Arts Road or Kirkwood Ave, or detour through campus.

Please take care when travelling through these areas – slow down, follow onsite signage and look out for others.

These changes are expected to be in place until early February when the project is completed, and the next stage of work on University Drive is expected to start on 9 January. Further information will be provided before the next stage starts – keep an eye out for further updates on Insider’s.

More information about the Uni-Cycle route is available on the Christchurch City Council website.

Uni Drive Stage 2

*Note – this update replaces a previous Uni-Cycle update posted on 9 December.  

Uni-Cycle work starts next week

Contractors will start construction work on the Uni-Cycle route  on Monday 21 November.

The Uni-Cycle route, which connects UC to the central city, will run along University Drive, Ilam Road and across Ilam Fields to Dovedale Ave.

Two crews will be working – one on University Drive and the second on Ilam Fields.

University Drive
Work will be carried out in three stages along University Drive starting from the Clyde Road end and moving towards Ilam Road.

During each stage a one-way system heading east (towards Clyde Road) will be in place in the area of work.

Stage one: 21 November – 21 December

  • Work will be carried out on University Drive between the entrance to Clyde (Arts) Car Park and Clyde Road.
  • A one-way system heading east (towards Clyde Road) will be in place on University Drive in the work area.
  • There will be no entry from Clyde Road onto University Drive.
  • Vehicles coming from Clyde Road should access the Clyde Car Park via Arts Road.
  • Vehicles exiting the Clyde Car Park onto University Drive will not be able to turn right (towards Ilam Road). Left turn only.
  • Two way traffic will remain on University Drive between Ilam Road and the east entrance to the Law Car Park.
  • The footpath will be closed on the south side of University Drive in the work area. Pedestrians will be detoured via the footpath that heads towards the Clyde Car Park.

UniCycleStageOne

Further information for stages two and three will be provided before each starts.

Ilam Fields
The existing path on the north side of Ilam Fields will be widened in sections. Pedestrians and cyclists using the path should follow any detours in place.

The work on Ilam Fields is expected to be completed by Christmas, and all work along University Drive is expected to be completed by early February 2017.

Please take care when travelling through these areas – slow down, follow onsite signage  and look out for others.

Uni-Cycle work starting mid-November

Christchurch City Council (CCC) expects to start construction work on the Uni-Cycle route, which will connect UC to the Central City, on 14 November.

The route runs along University Drive, Ilam Road and across Ilam Fields to Dovedale Ave. (See map below.)

The work is likely to impact traffic and pedestrians travelling through these areas. CCC is currently confirming the construction methodology and traffic management plan, however please note at this stage lane closures along University Drive are anticipated. There may also be disruption for those using the path on the north side of Ilam Fields.

Further details will be provided via the staff and student blogs as soon as the traffic management plan has been finalised.

In the meantime, to find out more about the Uni-Cycle route go the CCC website.

UniCycle route map