Haere-roa, the new UCSA building is starting to take shape – the structural frame has been completed, and roof and cladding works are almost complete with the building due to be weather tight early in the New Year. Internally the work continues at pace with good progress being made on pipework, ducts, cables and walls.

While work on Haere-roa is progressing, there have been some challenges along the way that have resulted in a delay to the construction programme. This means Haere-roa is now scheduled to open in Semester 2 2019.

UCSA’s offices and the Events Centre/Foundry will remain in their current locations during Semester 1 next year.