The Facilities Management (FM) Science Road / Erskine Carpark safety improvements and upgrades are progressing on schedule.

Current Works

  • A significant portion of the carpark will reopen for public use on Monday 15 December. Line-marking will be completed in the new year.
  • Science Road will return to usual 2-way traffic Monday 15 December.

Pedestrian Access

  • The existing 11-year-old temporary pedestrian walkway will be closed until the new shared pedestrian/cycle path is completed in the new year.
  • Site fencing will enclose the work area. Pedestrians will need to use paths along the southern boundary of the carpark and Science Road.

Next Focus

  • Works will shift to the new curb and channel alignment along the length of the FM building.

What You Need to Do

  • Observe entry/exit signage for open carparks.
  • Expect construction noise during the day.
  • Use alternative parking areas: Arts, Māori Study Centre, UCSA, and Dovedale Campus carparks.

Please direct all enquiries to fmassist@canterbury.ac.nz

Thank you for your continued understanding and cooperation as we work to improve safety and access in this area.