Clyde Road Now Open to 2-way Traffic!

Great news!

 Clyde Road (including Arts Road) is open to two-way traffic again approximately six (6) months ahead of schedule!

Creyke Road is also ahead of schedule and making strong progress with the majority of the works completed. The work on the eastern and western ends of the road is ongoing. We ask you to remain aware of the works still in progress. Multiple pipes are being laid at different depths and this requires

Dormer Construction will commence works on the Creyke/Maidstone/Ilam Roads intersection in approximately one month’s time. The intersection works are expected to take approximately four (4) weeks to complete, with ongoing works expected on Maidstone Road until mid-2026.

Please remain aware of works in progress and drive carefully and with patience through the works areas.

Facilities Management

Extension of Time for Concrete Repairs to Facade of Psychology and Sociology Laboratory – April 2025

Facilities Management contractors will continue & complete essential concrete repairs to the exterior of the Psychology and Sociology building between 22 April and 24 April.

Affected Buildings:

  • AR12 Psychology and Sociology Laboratory
  • AR06 Jane Soons
  • AR08 Ann Ballin
  • Forestry Road
  • Arts Road

The elevations, or site areas, to be repaired are shown with a blue dotted line on the inset site plan. Temporary work areas will be set-up and coned off to carry out these works.

Speech & Hearing Clinic: There will access to Entrance G on Thursday morning for appointments to take place.

While the works are in progress please follow all access signage. Do not enter any coned off work areas and be aware of all machinery in use on site.

Thank you for your consideration as we complete these repair works.

Please direct all enquiries to fmassist@canterbury.ac.nz

Facilities Management

 

 

 

Building Surveys Programme Including Exterior Rooves 23 April – 2 May

Facilities Management Building Surveyors will be undertaking surveys to the interiors and some exterior roof spaces on multiple buildings between Wednesday 23 April and Friday 2 May.

If you see staff on roof spaces across Campus during that time, it is likely that they will be the surveyors and will be following all working at heights safety protocol. If you are at all concerned, please contact UC Security 0800823637.

The purpose of the UC Building surveys is to complete a full visual assessment of the condition of the interior and exterior of the building. Surveyors will ensure that any photographs taken during the assessment are of the building and that persons are not identifiable in the photographs.

 Your support in ensuring that spaces are tidy and open for inspection will be appreciated.

 Please direct any enquiries to fmassist@canterbury.ac.nz.

 Thank you for your consideration as we undertake these required building surveys.