Category Archives: Behaviour and Responsibilities

Door Upgrade Haere-Roa

There will be a door outage in the Haere-Roa building between Monday 9 September and Thursday 26 September, while Facilities Management contractors upgrade the existing double doors at the eastern end of the Haere-Roa building (off University Drive) with automatic sliding doors. This will improve building accessibility.

The works will occur in two phases:

Phase 1

Start Date: 9/09/2024

Finish Date: 12/09/2024

Phase 2

Start Date: 23/09/2024

Finish Date: 26/09/2024

While the work is being completed technicians and tradespersons will be working from 7.30am to 5pm weekdays and building users will not be able to use the doors to the eastern end of the building for entry / exit of the building.

Use one of the alternate entry and exit points shown on the attached plan, and follow usual evacuation procedures in the event of an emergency.

After 5pm please enter the building through the main entrance.

Please direct any enquiries to fmassist@canterbury.ac.nz

Thank you for your consideration as we undertake these upgrade works.

Ngā mihi

Facilities Management

Notification of Ilam Wastewater Works – Temporary Access Re-direction University Drive

From Monday 2 September, the Christchurch City Council will start a significant wastewater upgrade in Ilam that will affect access to and from Ilam Campus.

The works will affect Creyke Road, Clyde Road through to the Maidstone Road / Waimairi Road intersection, and Clyde Road from Hinau Street to Creyke Road, and will be completed in three stages starting Monday 2 September and running until May 2026.

Works Stage 1:  2 September 2024 – December 2025

The initial stage includes work on Clyde and Creyke roads with traffic flowing north one way on Clyde Road and west one way on Creyke Road. See Christchurch City Council’s information here>

How this could affect you:

– No vehicle entry to Creyke Road from the Ilam Road intersection.

– No vehicle entry to Clyde Road from the Clyde Road / Kotare Street intersection.

– Left turn only onto Creyke Road from Montana Avenue, Engineering Road, and Forestry Road.

– On-street parking on Clyde Road and Creyke Road may be reduced.

– University Drive will be closed from Fine Arts Lane to Clyde Road, finishing late September

Regular updates on the project will be communicated here on Tūpono or can be found at ccc.govt.nz/Ilam-wastewater. Please direct any works enquiries to security@canterbury.ac.nz.

Puaka-James Hight lifts out of service – western end

The western lifts, closest to the Library main entrance in Puaka-James Hight, will be out of service for three weeks from 8am Monday 2 September until 5pm Wednesday 18 September to allow contractors to undertake a planned upgrade.

The western lifts are next to the western stairs, the women’s bathroom, and adjacent to the level 2 library reception. See image below.

 

 

 

 

During this time, please use the alternative three lifts or stairwell and follow usual evacuation procedures in the event of an emergency.

Please direct any enquiries to FMassist@canterbury.ac.nz

Thank you for your patience as we undertake these required upgrade works.

Ngā mihi,

The Facilities Management Team